The first of two tasks under a new cleanup agreement have come in ahead of schedule. Last Friday, Rayonier submitted its draft Work Plan, 37 days early. On March 17, 2010, Ecology received a draft table of contents for the Marine Data Summary report – also early.

The work plan is for collecting data on the upland portion (mill property) of the Study Area. The sampling will help Rayonier and Ecology understand the extent of contamination in that area, and begin planning for cleanup.

The ball is now in our court to get comments on both documents back to Rayonier.