Cleaning up: How a light rail project keeps a landfill site on track

How do you build light rail and widen a freeway along the edge of a well-managed former municipal waste landfill? Very carefully! 

And, with plenty of cooperation among public agencies.

We’re working to do exactly that with Sound Transit, the Washington State Department of Transportation (WSDOT) and Seattle Public Utilities (SPU).

Grassy land slopes from left to right to a freeway on the right. Above these, in the background, are green trees and a partly cloudy sky.
A grassy meadow covers the Midway Landfill, next to the I-5 freeway southbound lanes between Seattle and Tacoma. White pipes behind the fence are part of the system to collect landfill gas, given off by decomposing municipal solid waste below.

The site: a former landfill

The City of Seattle’s 60-acre Midway Landfill site adjoins the west side of I-5 in Kent. The landfill closed in 1983. Under our oversight, and review by the U.S. Environmental Protection Agency, SPU:
  •  Covered the landfill with an engineered, multilayered waterproof cap and a top layer of grass.
  • Installed a gas extraction system to control methane generated by material in the landfill.
  • Controlled surface water.
  • Fenced the landfill to limit access to the site.

These protective elements have been in place since 1992. SPU continues to monitor groundwater quality and landfill gas at the site, under a legal agreement with us, last updated in 2006.

A map shows the landfill in the center, with the freeway just to the right. A double yellow line shows the future path of light rail along the freeway at the landfill's edge. A red line shows the landfill boundaries. A blue line shows the work area for light rail construction.
Sound Transit will build light rail on the landfill's east side,
along I-5's southbound lanes. (Click or tap image to enlarge.)

Transportation projects

Two planned south King County transportation projects will run half a mile through the eastern edge of the landfill. Sound Transit plans to extend its Link light rail line from Angle Lake to Federal Way. WSDOT plans to widen a stretch of I-5 as part of its SR 509 Completion Project.  Preparation of the landfill for the two projects will be combined into a single project called FWLE/SR 509 Midway. FWLE stands for Federal Way Link Extension.

FWLE/SR 509 Midway will bring changes to the site. We’re developing legal agreements and engineering plans with all three parties – SPU, WSDOT and Sound Transit -- to ensure that the site’s environmental and public health and safety measures continue to function during and after construction.

The combined project will involve excavating some of the landfilled municipal waste, and will affect the landfill cap, the gas collection system, and surface water monitoring network. Because of this, we’re requiring:
  • Transfer of excavated municipal waste to an authorized landfill.
  • Restoration of disturbed portions of the landfill cap and other infrastructure.
  • Documentation of all required work for our review and approval.

Some of the site’s land ownership will change. Sound Transit will acquire part of a strip – for the light rail tracks – that now belongs to WSDOT and will assume responsibility for maintaining that portion of the landfill cap. Seattle will continue to operate surface water controls, the gas extraction system, and the ongoing monitoring program.

Plans and agreements available

We’re asking the public to review and comment on four documents that will govern how the FWLE/SR 509 project will be built, and how the site will be reconfigured:
  • Consent Decree Amendment:  update to our existing legal agreement with SPU.
  • Prospective Purchaser Consent Decree:  new legal agreement between us and Sound Transit.
  • Cleanup Action Plan Amendment:  describes actions we will require to maintain the integrity of the site’s protective elements during and after the proposed construction.
  • Public Participation Plan: explains how people can participate in the cleanup process.

Grassy land slopes from right to left toward a freeway on the left. Trees and a blue sky with a few clouds are in the background
Looking south across the Midway Landfill where it adjoins I-5.

Comments invited; public meeting planned

The comment period begins on Jan. 27 and concludes on Feb. 25, 2020. Comment online or mail comments to: Mark Adams, Site Manager; Dept. of Ecology; 3190 160th Ave. SE; Bellevue WA, 98008-5452.

We’re also inviting the public to a meeting and hearing. We, SPU, Sound Transit and WSDOT will give a short presentation and answer questions about the site and the projects. There will be time for giving oral comments.
  •  Tue., Feb. 11, 2020; 7 - 9 p.m.
  • Des Moines Elementary School, 23801 16th Ave. S.
  • Interpreter services will be available in Spanish, Korean, and Somali.
 We’ll review and respond to all comments received. We expect the new plans and agreements to be in place by mid-2020.

By Larry Altose, communications manager, Northwest Regional Office

More information





Monday, October 28, 2019

Cleaning up: An affordable housing milestone


A pair of street corners in southeast Seattle may not look like much right now, but they’re already a first-of-its-kind cleanup site for Ecology. Yet, it’s a contaminated site much like hundreds before it that have undergone cleanup and been put to new use. We’re opening a public comment period on a cleanup plan that marks an important an important step forward.  
A drawing of planned buildings, five stories on either side of an intersection.
The Maddux will provide affordable housing and street-level shops about a block from a Link light rail station.
Illustration courtesy of Mount Baker Housing Association.

A first

The Mount Baker Housing Association’s Maddux project is the inspiration for Washington’s Healthy Housing Remediation Program, which we developed in conjunction with the Washington State Department of Commerce. The program enables local governments and nonprofit organizations to obtain state funding to help offset environmental cleanup costs when redeveloping contaminated land for affordable housing.

Mount Baker acquired a cluster of lots where S. McClellan Street intersects with Martin Luther King Way S. The association plans 166 affordable units with street level retail a block from Sound Transit’s Mount Baker Link light rail station and near a variety of shopping and services.

Overcoming a common obstacle

These plans overlap with a costly problem that’s common to urban redevelopment. Previous use of the property – in this case a gas station and a dry cleaner – left contamination behind. The remediation program, building on earlier funding we’ve provided for the project’s cleanup, has enabled Mount Baker to proceed with more than $6 million in state assistance to hire consultants who evaluated the contamination, sifted through cleanup options and worked with us to propose a cleanup plan.

The former gas station at Martin Luther King and McClellan. The former dry cleaner is across McClellan at far left. Ecology photo.
We’re asking the public, as part of the state Model Toxic Control Act cleanup process, to review those studies, the plan, proposed updates to our legal agreement with Mount Baker, and environmental review documents we’ve prepared.

That comment period runs through November 26, 2019.

Historic releases from gas stations and dry cleaners are the most common types of cleanup sites in Washington. Current laws on handling cleaning chemicals and managing underground storage tanks prevent these problems at today’s cleaners and fill-up stations.

A cleanup plan that fits the project

The gas station cleanup will primarily involve excavation of soil in and around areas where underground tanks and system piping once were.

The dry cleaner’s contamination requires a more complex approach. The solvents that were used mix readily into water. Even a small spill or leak into the ground can spread over a wide area if it enters the flow of groundwater. That’s what happened here (see the map below), and the Maddux development will incorporate features that factor in a cleanup process that may continue for several years.

A map shows property parcels at the intersection of McClellan Street and Martin Luther King, Junior, Way. Shading shows areas at a former dry cleaner and at a former gas station where soil will be removed. Other shading shows the estimated location of groundwater that is contaminated with solvent chemicals.
The cleanup plan will protect people from contaminated
groundwater, shown in blue. Processes to break down
the plume’s solvents will proceed over several years.
Illustration courtesy of Mount Baker Housing Association.
Excavation of the contaminated soil under the dry cleaner and adjacent parcels will remove the source of the groundwater contamination. This will help slow or stop the expansion of the plume of solvent-contaminated groundwater that extends under S. McClellan Street, part of the former gas station and under an adjoining stretch of Martin Luther King Way S.

The rest of the plan allows the project to proceed and cleanup to continue without disrupting traffic on the two streets:
  • Because the solvent compounds can release vapor that can rise through the soil, the project will be engineered with capping, vapor barriers and sub-slab ventilation. The property deed will prohibit future modifications that change these protections without notifying us and obtaining our approval.
  • Long term monitoring will provide information on how well the cleanup treatments are working and track the breakdown of the solvents.
  • After 5 years of monitoring, the time to reach cleanup in the groundwater will be recalculated. If it is determined to be too slow, Mount Baker will inject a chemical (such as zero valent iron) into the groundwater that aids in the breakdown the contaminants. Bacteria that’s naturally present in soil also helps by feeding on the solvent chemicals, breaking them down biologically.

We will review the monitoring data and the condition of the site every five years to determine how well the plan is working and whether any changes are needed. We’ll issue a report on these periodic reviews and ask for public comment each time.

Two people operate a soil core sampling apparatus. On the left a person kneels, and on the right a person stands. Both hold parts of the equipment. Both are dressed in helmets and safety vests. They are inside a room with dry cleaning equipment.
Technicians for a consulting firm drill below the floor 
of a former dry cleaner to gather environmental samples.
Photo courtesy of Mount Baker Housing Association.

Public meeting

Along with the comment period, we’re hosting a public meeting and open house. Our cleanup experts will be there, along with representatives from Mount Baker and their environmental consultants. 

We’ll have displays about the project and the cleanup plan and will be glad to discuss the cleanup and answer questions. We’ll also give a presentation and take audience questions. Translation and interpreter services will be available in Spanish, Chinese, Vietnamese, and Khmer.

By: Larry Altose, Northwest regional communications manager

More information:

The documents out for comment:
A fact sheet about the project's cleanup process is available in Chinese, English, Khmer, Spanish and Vietnamese.

Other links:

Monday, June 24, 2019

Cleaning up: In the footprint of an old corner gas station


One of the largest categories of cleanup sites, statewide, is former gas stations. Old-school underground storage tanks were prone to leaking into the surrounding soil. Tank owners today must follow laws and regulations to prevent leaks and spills. Many of the places once occupied by a corner gas station have since become desirable redevelopment locations. We're taking public comment and inviting you to a community meeting about one example that’s unfolding now in Seattle.

A line of shops with a few cars angle-parked in front.
A row of convenience shops at the station, toward the end
of its heyday.

First, some history

There was a gas station operating under the Texaco brand at Queen Anne Avenue North and Roy Street from 1927 to 1993. After the pumps closed, a deli operated on the property to 2018.

In 1986 Ecology responded to complaints of gasoline odors at the adjacent Monterey Apartments. An investigation we conducted from 1986 to 1990 revealed the gas station as the source. We installed two wells to remove petroleum from groundwater.

When the pumps closed and the underground tanks were removed in 1993, we found soil and groundwater contamination. We installed and operated a system from 1993 to 1997 to extract vapor and recover groundwater.

Texaco’s successor, Chevron Environmental Management Company (CEMC), upgraded and operated the system from 2003 to 2008 under Ecology’s Voluntary Cleanup Program. CEMC also mapped areas where low levels of contaminated groundwater extend into part of the surrounding neighborhood. Buildings over this plume and adjacent to the former gas station -- the Del Roy and Monterey apartments -- received vapor tests in 2009 that found indoor air quality within health thresholds. 

Aerial map with a yellow line surrounding about half a dozen properties.
Roystone on Queen Anne, LLC plans to clean up contamination at the former Texaco station. Chevron Environmental Management Co. will take steps needed for final cleanup of the entire site.

This corner’s about to change

Fast forward to 2019, and a developer named Roystone on Queen Anne, LLC has acquired the old gas station lot. The company plans to re-develop the vacant property into a multistory mixed-use building.

We’ve negotiated an agreement with both companies. Roystone will clean up contaminated soil and groundwater on its property to meet state cleanup standards in conjunction with excavation for its project. That cleanup is called an interim action.

Meanwhile, CEMC will proceed with the steps needed for final cleanup of the entire site. These include a site assessment, called a remedial investigation, a feasibility study of cleanup options, and a draft cleanup action plan.

What’s your take?

Closed retail store fronts, with an empty parking lot in the foreground, behind fabric-covered chain link fencing.
These empty shops will give way to cleanup work as part of re-developing
the site into a multi-story mixed-use building.
We’re inviting you to learn about these plans and tell us your thoughts about them. We’re taking comments through July 23, 2019 on the interim action plan, a legal agreement called an agreed order with the two companies, environmental reviews we’ve conducted, and a proposed public participation plan, which describes how we’ll work to inform people about the cleanup.

Our website has links to all of these documents, to our online public comment app for this site, and contacts for answers to questions. We’ve also placed copies of the documents at Seattle Public Library’s Queen Anne Branch, 400 W. Garfield St.

Pleased to see you

We’re hosting a public meeting to provide information, answer questions about the site and the cleanup process, and to take comments. The meeting will take place from 6 to 8 p.m., Thu., June 27, 2019 at the Maxwell Hotel, 300 Roy St. in Seattle.

Cleanup site information



By: Larry Altose, communications manager, Northwest Region