One of the largest
categories of cleanup sites, statewide, is former gas stations. Old-school
underground storage tanks were prone to leaking into the surrounding soil.
Tank owners today must follow laws
and regulations to prevent leaks and spills. Many of the places once
occupied by a corner gas station have since become desirable redevelopment
locations. We're taking public comment and inviting you to a community meeting about one example that’s unfolding now in Seattle.
A row of convenience shops at the station, toward the end
of its heyday. |
First, some history
There was a gas station
operating under the Texaco brand at Queen Anne Avenue North and Roy Street from
1927 to 1993. After the pumps closed, a deli operated on the property to 2018.
In 1986 Ecology
responded to complaints of gasoline odors at the adjacent Monterey Apartments.
An investigation we conducted from 1986 to 1990 revealed the gas station as the
source. We installed two wells to remove petroleum from groundwater.
When the pumps closed
and the underground tanks were removed in 1993, we found soil and groundwater
contamination. We installed and operated a system from 1993 to 1997 to extract
vapor and recover groundwater.
Texaco’s successor,
Chevron Environmental
Management Company (CEMC), upgraded and operated the system from 2003 to
2008 under Ecology’s Voluntary
Cleanup Program. CEMC also mapped areas where low levels of contaminated
groundwater extend into part of the surrounding neighborhood. Buildings over
this plume and adjacent to the former gas station -- the Del Roy and Monterey apartments -- received vapor tests in 2009
that found indoor air quality within health thresholds.
Roystone on Queen Anne, LLC plans to clean up contamination at the former Texaco station. Chevron Environmental Management Co. will take steps needed for final cleanup of the entire site. |
This corner’s about to change
Fast forward to 2019,
and a developer named Roystone on Queen Anne, LLC has acquired the old gas
station lot. The company plans to re-develop the vacant property into a
multistory mixed-use building.
We’ve negotiated an
agreement with both companies. Roystone will clean up contaminated soil and
groundwater on its property to meet state cleanup standards in conjunction with
excavation for its project. That cleanup is called an interim action.
Meanwhile, CEMC will
proceed with the steps needed for final cleanup of the entire site. These
include a site assessment, called a remedial investigation, a feasibility study
of cleanup options, and a draft cleanup action plan.
What’s your take?
These empty shops will give way to cleanup work as part of re-developing the site into a multi-story mixed-use building. |
Our website
has links to all of these documents, to our online public comment app for this
site, and contacts for answers to questions. We’ve also placed copies of the
documents at Seattle Public Library’s Queen Anne Branch, 400 W. Garfield St.
Pleased to see you
We’re hosting a public
meeting to provide information, answer questions about the site and the cleanup
process, and to take comments. The meeting will take place from 6 to 8 p.m.,
Thu., June 27, 2019 at the Maxwell Hotel, 300 Roy St. in Seattle.
Cleanup site information
By: Larry Altose,
communications manager, Northwest Region
No comments:
Post a Comment
We will not post comments with links to commercial sites, so please do not include them! Thank you.
(Comments Policy)